Lisbon Airport's Stopgap: a €233M South Pier, €20M on Terminal 2 and €388M Planned to 2028

The biggest contract since VINCI bought ANA adds boarding bridges, not flights. Capacity money is €64M of Lisbon's €388M plan, and the steps to 42 movements an hour are still uncosted.

Key figures

Main works contract
€233M ↑Signed 27 Nov 2024 with a Mota-Engil-led consortium for the South Pier (33,000 m², 10 bridges, 12 stands); VINCI calls it its largest capex contract since buying ANA.
Capacity money, Lisbon 2026–28
€64M of €388M →ANA's plan (ECO, 6 Oct 2026): €231M operational improvement, €64M capacity projects, €93M unassigned (derived). The 40 and 42 steps have no published cost.
Declared capacity
38 movements/h →Unchanged since before VINCI bought ANA; ANA says 42 will be the level at transfer to the new airport, and 45 has no date.
ANA network capex 2025
€128M ↑+27% on 2024 (ANA S.A. basis); plan rises to €165M, €215M and €307M in 2026–28, about €1.77 per passenger in 2025 (derived).
Dividends ÷ capex, 2023–24
3.9× ↑€728.4M paid in dividends (Observador) against €187.2M of ANA S.A. capex over the same two years (derived).
Pier life before new airport
7–9.5 years ↓Pier due end-2027; Luís de Camões scheduled for 2035 (government) to mid-2037 (ANA) (derived).

Key takeaways

  • ANA signed a €233M contract on 27 Nov 2024 with a consortium of Mota-Engil, VINCI Construction Grands Projets, Alves Ribeiro and HCI for a 33,000 m² South Pier with 10 boarding bridges and 12 stands, due end-2027 (VINCI; Jornal de Negócios).
  • ANA's chief executive described the pier in December 2022 as not a capacity expansion; Lisbon's declared capacity is still 38 movements an hour.
  • Four figures describe the programme: €233M (contract), €250M (South and Central piers), about €300M (all Terminal 1 works) and more than €300M (VINCI's UPGRADE plan); none is an audited total.
  • ANA plans €687M across its ten airports in 2026–28; Lisbon gets €388M (56%), of which €231M is operational improvement and €64M capacity projects (ECO, 6 Oct 2026).
  • Terminal 2's enlarged Schengen area opened on 7 Jan 2026 after a €12M phase; VINCI puts total Terminal 2 investment since 2020 at €20M.
  • The 2019 Montijo agreement promised €650M for Portela and 48 movements an hour; it collapsed in March 2021 after two municipalities objected, and the 2026 plan targets 42 at transfer.
  • Lisbon's charge cap rises at inflation minus 2% in 2024–2028 because ANA's investment ratio R was below 0.2 in 2018–2022; capex in 2023–2027 sets the factor for 2029–2033 (ANA annual reports).
  • Claims that ANA is investing €1bn in Portela, that the pier opens in 2026, that Lisbon will handle 50M passengers or reach 45 movements by 2030 are not supported by any primary source.

The largest construction contract at Lisbon airport since VINCI bought the operator ANA in 2013 adds no hourly flights. The €233 million deal signed on 27 November 2024 pays for a 33,000 m² South Pier with 10 boarding bridges and 12 aircraft stands. When ANA's chief executive Thierry Ligonnière first described the project in December 2022, he said plainly that it was not a capacity expansion. Humberto Delgado's declared capacity was 38 movements an hour then and is 38 movements an hour now.

The capacity money is a separate and much smaller line. ANA's investment plan for 2026–28, filed with its charges consultation and reported by ECO on 6 October 2026, gives Lisbon €388 million, 56% of the €687 million planned across its ten Portuguese airports. Of that, €231 million is an "operational improvement plan" for the existing terminal and €64 million is labelled as capacity projects. The steps from 38 to 40, 42 and perhaps 45 movements an hour, which the government ordered in May 2024, still have no published cost.

This article follows the money and the works: what the South Pier and the Terminal 2 upgrade buy, how the plan shrank from the €650 million promised for Portela in 2019, who pays through airport charges, and how long the new assets will be used before the new Luís de Camões airport replaces them. Traffic, slots and punctuality are covered in our Lisbon airport capacity analysis; here they appear only where they explain the investment.

Four price tags for one programme

Press coverage of the Lisbon works uses at least four figures, and each describes a different scope. €233 million is the main contract, signed with a consortium led by Mota-Engil that also includes VINCI Construction Grands Projets, Alves Ribeiro and HCI. VINCI Construction belongs to the same group as ANA's owner, VINCI Airports. €250 million is ANA's "global" value for the South Pier and the renovation of the Central Pier, first given with its 2024 results in May 2025. About €300 million is the value of all works under way at Terminal 1, according to ANA in January 2026 (Jornal de Negócios, 7 January 2026). More than €300 million is VINCI's own figure for its whole "UPGRADE" plan at the airport, in a release of 16 January 2026.

None of these is an audited total. They also predate the contract: Ligonnière spoke of €200–300 million in December 2022, ANA planned about €200 million for Terminal 1 in 2024 when it presented its 2023 results, and Jornal Económico used €300 million in February 2024. A fifth €300 million figure belongs to a different subject entirely. The government's technical commission estimated in 2023 that demolishing Portela after the new airport opens would cost about €300 million of public money.

By 7 January 2026 ANA had executed €40 million of the South Pier project, with 150 workers on site and a peak of 600 expected. A €16 million package for the departures check-in area was due to start next. In August 2026 Martifer disclosed in its half-year report that it had won the steel structure, roofing and façades for the South apron and the South and Central piers: 3,924 tonnes of steel, 17,700 m² of façade and 45,000 m² of cladding. Martifer did not disclose the value.

Every published cost for the Humberto Delgado works, 2019–2026
DateFigureWhat it coversSource
8 Jan 2019€650MPortela phase 1 within the €1.15bn Montijo agreement (never executed)VINCI; Observador
9 Dec 2022€200–300MT1 south extension, more than 10 bridge gates, new apron; "not a capacity expansion"Ligonnière via Lusa
23 Feb 2024€300MT1 enlargement and 10 boarding bridgesJornal Económico
27 Nov 2024€233MMain contract: South Pier, Central Pier link, South bus gatesVINCI Airports
23 May 2025€250MSouth Pier plus Central Pier renovation; T2 €12MANA results via DN/Lusa
10 Jul 2025Up to €30MMoving the Figo Maduro military aerodrome to Montijo (state money)Council of Ministers via RTP
7 Jan 2026≈€300M / €20MAll T1 works under way / T2 since 2020; capacity value "not yet defined"Jornal de Negócios; Observador
16 Jan 2026More than €300MVINCI's whole UPGRADE plan at LisbonVINCI Airports
6 Oct 2026€388MLisbon 2026–28: €231M operational plan, €64M capacity, €93M unassigned (derived)ANA plan via ECO
Figures as reported; none is an audited programme total. The 2019 deal is reported as €1.15bn (VINCI), €1.3bn (Observador) and €1,326M (ECO, citing Público) depending on whether Air Force compensation and road works are included.

What the South Pier buys

The pier extends Terminal 1 to the south by about 600 linear metres. VINCI's contract release lists 33,000 m² of new building, 10 boarding bridges, 12 aircraft stands, a remodelled Central Pier linked to the new structure, and a redesign of the South bus gates. Construction was planned for December 2024. A challenge by the Ministério Público delayed the start by several months without stopping it, and completion is now scheduled for the end of 2027. ANA has not said which part of the pier will serve Schengen or non-Schengen flights.

Divided out, the main contract costs about €7,060 per square metre of new pier and €23.3 million per boarding bridge (both derived). Those ratios overstate the per-unit price, since the contract also covers the Central Pier and the bus gates, but they show the scale. One discrepancy remains open. ECO reported on 28 September 2026 that the Terminal 1 works include "11 more jet bridges and three parking stands", against the contract's 10 bridges and 12 stands. We use the contract figures.

The main gain is fewer bus transfers. Archived ANA pages put Terminal 1 at about 47 departure gates, of which about 17 had boarding bridges. If none of those is lost in the Central Pier rework, the airport would have about 27 bridge gates at the end of 2027 (derived, indicative). Jornal de Negócios reported that the 10 bridges remove "the need to use buses" at those gates. The contract also rebuilds the South bus gates, so bus boarding continues across the rest of the terminal. ANA publishes no share of passengers boarded by bus, and no figure for how many more passengers an hour the pier can process.

ANA's investment, 2019–2028: flat for years, then a planned jump

Capital spending across ANA's ten Portuguese airports, as reported and as planned. Lisbon is not broken out in any annual report; the 2026–28 plan is the first to give Lisbon's share.

Compiled by Panos Bampalis, Portugal Trip Planner · Sources ANA annual reports 2020, 2023, 2024 and Integrated Report 2025; ANA charges-consultation document via ECO (6 Oct 2026) and Jornal de Negócios; Observador (26 May 2025) · Verified October 2026
€388M
Lisbon plan 2026–28
€64M
of it tagged to capacity
3.9×
dividends ÷ capex 2023–24
€1.77
network capex per passenger 2025
YearCapexScale (2028 plan = full bar)What the figure covers
2019Not publishedGAPANA reports €38.4M of cash payments for fixed assets; not a capex measure
2020€76.2M
ANA S.A.; €60.3M of it at Lisbon, Porto and Faro combined; about €16M spent on Montijo by end-2020
2021–22Not retrievedGAPAnnual-report investment sections could not be read
2023€86.4M
ANA S.A. (group €89.6M). ANA had planned ≈€200M for Lisbon T1 alone in 2024
2024€100.8M
ANA S.A. (group €105.0M); €4.7M of it on Terminal 2
2025€128M
+27% on ANA S.A. 2024; the integrated report speaks of a €131M plan
2026 plan€165M
Plan, current prices, excl. VAT
2027 plan€215M
Plan; South Pier due end-2027
2028 plan€307M
Plan; 2026–28 total €687M, of which Lisbon €388M (56%)

← Scroll to see all columns

💡 The money arrives late in the bridge period. ANA spent about €87–101M a year in 2023–24 while paying €728.4M in dividends to VINCI over the same two years. The plan triples annual spending by 2028, but the pier opens at the end of 2027 and the new airport is scheduled for 2035–2037, so the peak year of investment at Humberto Delgado falls seven to nine years before the airport is due to close.
2023–24 capex is ANA S.A.; group figures are slightly higher (€89.6M, €105.0M). The +27% for 2025 matches the ANA S.A. 2024 base (€100.8M); on the group base it is +21.9% (derived). 2026–28 figures are ANA's plan in its charges consultation, excluding reduced-mobility assistance and security, and are not realised spending. Dividends: Observador, 26 May 2025. Capex per passenger: €128M ÷ 72.47M ANA passengers (derived). Lisbon's €388M splits into €231M "operational improvement plan", €64M capacity projects and €93M not assigned in the press report (derived).

Terminal 2: €20 million on a terminal with a closing date

Terminal 2 opened in 2007 for low-cost airlines and is reached from Terminal 1 by shuttle. On 7 January 2026 ANA inaugurated an enlarged Schengen departure area there with four new gates, seven renovated ones and biometric boarding at every gate. The phase cost €12 million, of which €4.7 million was spent in 2024. VINCI's release of 16 January 2026 puts total investment in Terminal 2 since 2020 at €20 million. Press reports used one figure or the other, often without saying which.

ANA's expansion report of 31 July 2025, later posted by the transport institute IMT, says Terminal 2 needs no further building to support 45 movements an hour. It proposes three remote stands for medium-sized aircraft west of the terminal. No closure of Terminal 2 is planned before the airport as a whole is decommissioned. Its border post has one exit control with four manual and six automated positions (Euronews, 8 December 2025).

The capacity half: 38, 40, 42 and maybe 45

The government ordered the capacity increase in two resolutions. RCM 201/2023, published on 28 December 2023, set a list of works with deadlines, including a rapid-exit taxiway and multiple runway entries. RCM 67/2024, published on 27 May 2024 alongside the decision to build the new airport, set a target of up to 45 movements an hour plus two at Cascais. ANA delivered its plan on 1 August 2025. The government announced receipt on 5 August without publishing a cost, and the report reached the public only when IMT posted it in February 2026.

ANA's report sizes the airside need at 98 stands for 40 movements an hour, 103 for 42 and 106 for 45. The two higher steps depend on a new North apron and pier, which requires clearing the military aerodrome at Figo Maduro and moving cargo to the old runway 17 threshold. A new control tower east of runway 02/20 is the base case. The airspace sets its own ceiling: NAV's Point Merge design, live since May 2024, is limited to 46 movements an hour combined, and the 42 and 45 scenarios exceed it unless NAV expands the airspace. The Council of Ministers approved up to €30 million on 10 July 2025 to move Figo Maduro to Montijo by the end of 2028.

The licensing has been slower than the building. On 22 January 2024 the environment agency APA ruled that the South Pier, Central Pier and South apron did not need an environmental impact assessment. On 2 December 2024 it ruled the opposite for the outer taxiway, the Taxiway U extension and multiple entries to runway 20, because those works allow more flights; the study had to use 38 movements as its baseline and assess up to 45. In January 2026 ANA agreed with APA to split the assessment in two. The study for 38 to 40 was filed in early June 2026, with works from early 2027 if approved. The study for 40 to 42 is due in early 2027.

The 45 target has become less certain. Speaking to Parliament on 28 January 2026, Ligonnière described 42 as the level the airport would run at when traffic moves to the new airport and did not mention 45. ANA chairman José Luís Arnaut repeated "42, and later 45" in September 2026, saying the conditions depended on NAV. The secretary of state said in January 2026 that the value of the capacity expansion was "still undefined". The infrastructure minister's target for the existing airport is 40–45 million passengers a year, against 36.1 million in 2025.

Lisbon's capacity steps: status in October 2026
StepWorksLicensingDateCost
38 (today)Declared since before 2013; 93% used in 2023n/an/an/a
38 → 40Taxiway U, outer taxiway, multiple entries to runway 20EIA filed June 2026; no decision foundWorks from early 2027Not published
40 → 42North apron and pier; Figo Maduro clearedEIA due early 2027No dateNot published
42 → 45Airspace beyond Point Merge's 46 combined limit; new towerNot startedNo dateNot published
Sources: APA screening decisions (22 Jan 2024; 2 Dec 2024); ANA expansion report (31 Jul 2025, via IMT); Observador and Sábado (28 Jan 2026); ECO (5 Jun and 28 Sep 2026). Passenger effects at the 2025 passengers-per-movement ratio are in our capacity article.

From €1.15 billion to €233 million

The current programme is the smaller survivor of an older one. On 8 January 2019 ANA and the State signed a €1.15 billion agreement, entirely privately financed, to be spent by 2028: €650 million for phase 1 of Humberto Delgado and €500 million for a civil airport at the Montijo air base, plus €156 million for Air Force compensation and access works. Portela was to reach 48 movements an hour (VINCI; DN gave 44) and Montijo 24. The government targeted 2022 for Montijo's opening. The Portela list included more stands (60 to 89), new piers, more contact stands, new taxiways, the closure of runway 17/35 and the removal of Figo Maduro.

The plan collapsed on 2 March 2021, when the regulator ANAC refused to assess Montijo because two affected municipalities, Moita and Seixal, had issued negative opinions. ANA had spent about €16 million on Montijo by the end of 2020. Some of the 2019 Portela items happened anyway. Runway 17/35, which carried 0.1% of flights in 2018, was closed for good in 2019, and two rapid-exit taxiways were built at night in the first half of 2020. Most of the rest reappears in the 2023 and 2024 resolutions on a later timetable: deadlines originally set for 2018–2021 now run to 2025–2027.

The Portela plan in 2019 and in 2026
Item2019 agreement2026 position
Money for Portela€650M by 2028€233M contract; ≈€300M T1 works; €388M plan 2026–28
Target movements an hour48 (DN: 44)42 at transfer; 45 undated
Second airportMontijo, 24 movements, target 2022Luís de Camões, ANA mid-2037, government 2035
Stands60 → 8998 / 103 / 106 for 40 / 42 / 45 (ANA plan)
Figo MaduroTo be relocatedTo Montijo by end-2028, up to €30M of state money
FinancingPrivate, concession to 2062 unchangedPrivate; ANA's request to extend to 2092 is for the new airport and unapproved
2019: VINCI press release and Observador, 8 Jan 2019; DN, 3 Jan 2019. 2026: VINCI, ANA plan via ECO (6 Oct 2026), ANA in Parliament (28 Jan 2026), Arnaut via ECO (28 Sep 2026).

Who pays: the R factor and the charge cap

Lisbon's charges are not set on a regulated asset base. The concession caps the average regulated revenue per passenger for the Lisbon group, which includes Madeira, the Azores and Beja, and indexes the cap to EU inflation. Since 2024 the index is adjusted by a ratio called R: eligible capital investment divided by the Lisbon group's EBITDA over the previous five years. If R is 0.8 or more, the cap rises at inflation plus 1% a year. Below 0.2 it rises at inflation minus 2%.

ANA's annual reports for 2023 and 2024 state that R was below 0.2 for 2018–2022, so the Lisbon group cap moves at inflation minus 2% for 2024–2028. In other words, the low investment of the years after Montijo's collapse is now holding Lisbon's charges down. The same reports say eligible capex and EBITDA for 2023–2027 will set the factor for 2029–2033. ANA has not said so, but the arithmetic means the South Pier and the 2026–28 plan can raise allowed Lisbon charges from 2029, six to eight years before the planned move to Luís de Camões (our inference). ANA's 2022 report describes the 2023 cap as "inflation plus 2%", which conflicts with the later reports; we have not resolved it.

The numbers behind the cap are easy to confuse. The authorised 2025 cap for the Lisbon group was €14.652 per passenger, and the group collected €14.59. Lisbon airport on its own collected €15.35 (ANA regulated-revenue report, 20 May 2026). ANA's proposal for 2027 is a group cap of €14.80, with Lisbon's charges up 0.67%, still awaiting ANAC. At €15.35 across 36.1 million passengers, Lisbon generated about €554.6 million of regulated revenue in 2025, so the €233 million contract equals about five months of it (derived).

The spending also has to be read against payouts. ANA S.A. invested €86.4 million in 2023 and €100.8 million in 2024 across all its airports, while paying €728.4 million in dividends over the same two years (Observador, 26 May 2025): 3.9 times its capex (derived). ANA's group net profit was a record €599.3 million in 2025. The Tribunal de Contas found in January 2024 that the 2012 privatisation had not safeguarded the public interest; ANA's chairman told Parliament in June 2024 that some investments had been postponed "in agreement with governments".

Where ANA's €687M goes, airport by airport

ANA's 2026–28 investment plan set against each gateway's 2025 traffic, its growth since 2019 and the constraint our earlier airport articles identified. Lisbon gets the most money; per passenger it ranks third.

Compiled by Panos Bampalis, Portugal Trip Planner · Sources ANA charges-consultation plan via ECO (6 Oct 2026); Eurostat avia_paoa (2019, 2025); Portugal Trip Planner airport series (Oct 2026) · Verified October 2026
AirportCapex 2026–28SharePassengers 2025vs 2019Capex per 2025 passengerBinding constraint (series finding)
LisbonTHIS ARTICLE€388M
56.5%36,083,879+15.7%€10.7538 movements an hour; 93% used (2023)
Azores (4 ANA airports)€78M
11.4%3,308,549+31.7%€23.58Ryanair exit, Mar 2026; Q2 traffic −11%
Madeira + Porto Santo€57M
8.3%5,634,831+66.6%€10.12Wind limits at Funchal
Faro€63M
9.2%10,349,949+14.3%€6.09Seasonality: August 4.37× February
Porto€80M
11.6%16,923,253+28.3%€4.73Runway 24 → 26 movements an hour (end-2026)
Beja€3M
0.4%3,120+18.0%€961.54Almost no scheduled traffic
Ten ANA airports€687M100%72,303,581+21.9%€9.50€18M of the €687M is not assigned to an airport in the press report (derived)

← Scroll to see all columns

💡 Lisbon's share of the money matches its share of the problem, but most of it is not aimed at capacity. Lisbon takes 56% of the plan with 50% of ANA's passengers. Only €64M of its €388M is labelled as capacity work, and that line has to fund the steps from 38 to 42 movements an hour, which ANA has not yet costed. Porto, the fastest-growing mainland airport and the one with a runway upgrade under way, receives the least per passenger.
Capex is ANA's plan for three years at current prices, excluding reduced-mobility assistance and security. "Capex per 2025 passenger" divides the three-year plan by one year's passengers (derived). Passengers are Eurostat totals at ANA's airports; Madeira adds Funchal (5,390,975) and Porto Santo (243,856); the Azores are Ponta Delgada, Horta, Santa Maria and Flores. ANA's own 2025 counts are slightly higher (Lisbon 36,126,000). Growth since 2019 derived from Eurostat. Beja's per-passenger figure reflects a civil terminal with 3,120 passengers in 2025. Shares computed on €687M; the press report gives Lisbon as 56%.

Across the network the planned spending is uneven. Lisbon receives €10.75 per 2025 passenger over the three years, Porto €4.73 and Faro €6.09 (derived). Porto has grown 28.3% since 2019 against Lisbon's 15.7%, and our Porto airport article found its runway capacity rising from 24 to 26 movements an hour at the end of 2026. Faro's binding problem is seasonality, as the Faro airport analysis showed, so its lower figure is less surprising. The Azores receive the most per passenger, €23.58, in the year after Ryanair left.

How long the stopgap has to last

The new pier opens at the end of 2027. ANA's technical report schedules Luís de Camões for mid-2037, or late 2036 with faster approvals; the government's planning date is 2035 and the minister has asked for 2034. That leaves seven to nine and a half years of use for the pier before traffic moves (derived). Our new-airport tracker covers why each of those dates is contested.

What happens to the assets at closure is not public. A legal opinion prepared for the government's technical commission, reported by ECO in December 2023, says the State may end the Humberto Delgado concession before commercial flights stop, with compensation due to the concessionaire, and that changes requested by the State trigger financial rebalancing. No published clause sets a residual value for the stopgap investments. The land is public. The infrastructure minister said in October 2025 that it would be cleaned up for housing, green space and a riverside park, and "will not be used to pay for the new airport".

Other cities have run the same race with less money. Berlin's operator planned up to €50 million to modernise Tegel around 2013. BER then opened about nine years late, Tegel carried a record 24.2 million passengers in 2019, and it closed on 8 November 2020; the site is becoming housing and a technology campus. Hong Kong chose Chek Lap Kok in October 1989 and closed Kai Tak on 6 July 1998. Istanbul's Atatürk was running far above its design capacity when traffic moved to the new airport in 2019, and its operator TAV received €389 million for the 18 months it lost on its lease. Mexico City is the case after cancellation: it is spending about MXN 10 billion remodelling its existing airport after scrapping the Texcoco project in 2018.

Airports that waited for a replacement: what was spent on the old one
AirportDecision to replacementSpending on the old airportWhat happened
Lisbon Humberto Delgado2024 decision; opening 2035–2037€233M contract; ≈€300M T1 programme; €388M plan 2026–28Pier due end-2027; land returns to the State
Berlin TegelBER opened ≈9 years late (2020)Up to €50M planned (≈2013)Closed Nov 2020; housing and tech campus
Hong Kong Kai TakOct 1989 → Jul 1998Not publishedClosed 1998; cargo terminal briefly reopened
Istanbul AtatürkNew airport Oct 2018; full move Apr 2019Not published€389M compensation to TAV; national park
Mexico City AICMReplacement cancelled 2018MXN 10bn remodel; MXN 6.5bn phase 1 (2025–26)Still the main airport; cancellation cost MXN 332bn (ASF)
Sources: dpa via Aero International (Tegel, undated, about 2013); Flughafen Berlin Brandenburg; The Local (12 Oct 2020); HK Environmental Protection Department; Journal de l'Économie (29 Dec 2019); Expansión Política (30 May 2026); ASF via El CEO (18 Feb 2022). Atatürk's design capacity is not confirmed by a primary source.

What passengers get in the meantime

Lisbon ranked 274th of 279 airports in AirHelp's 2026 score, down from 244th of 250 in 2025, and 91st in Skytrax's 2026 World Airport Awards. Both rankings rest heavily on punctuality, where Lisbon had the lowest departure performance among large European airports in 2024 and 2025. Border queues added to the pressure after the EU's Entry/Exit System began on 12 October 2025. The government suspended it at Lisbon for three months from 30 December 2025, began enlarging the border areas on 29 May 2026, and cited works in operational areas as one cause of 90-minute queues on 17 May 2026. The police reported arrival waits of 30 to 60 minutes at the three main airports at the end of May.

The works will not change the runway for at least another year. Lisbon's low-cost share of 24% in mid-2026 reflects the same constraint: without spare slots, airlines that want to grow in Portugal have done so at Porto and Faro. The pier improves how passengers board aircraft that already have slots. More flights depend on the environmental decisions for 40 and 42 movements, on NAV's airspace, and on who controls TAP's slot portfolio after the TAP privatisation.

Noise, the courts and the risks to the timetable

The Ministério Público's action at the Supreme Administrative Court, reported on 9 January 2025, asks for the APA exemption of January 2024 and RCM 201/2023 to be annulled and for no significant expansion to proceed without a full environmental assessment. It argues that the works were split into pieces to avoid one; the last full assessment of the airport dates from 2006. The action did not request an injunction, and we found no ruling by October 2026. The NGO ZERO asked the court to decide urgently in August 2025.

The noise programmes are small next to the construction budget. The state-funded Menos Ruído programme has €10 million for insulation, with protocols signed on 22 January 2026 with Almada, Lisbon, Loures and Vila Franca de Xira; Lisbon's share is €2,798,730 and individual grants are capped at €1,000, €800 or €600. ANA has proposed €2.5 million for insulation through the same fund and about €1 million, then up to €4 million, for schools and health buildings. Lisbon's mayor Carlos Moedas has opposed 45 movements an hour and asked for compensation from VINCI. ZERO counted about 150 night movements a week in summer 2025 against a legal limit of 91.

The risks to the programme are specific. A court ruling against the 2024 exemption would reach works already built. A negative or delayed decision on the 38 to 40 study would push the first capacity step beyond 2027. NAV's airspace limits make 45 movements uncertain whatever ANA builds. A later opening of Luís de Camões would lengthen the life of the stopgap and strengthen the case for more spending at Portela; an earlier one would shorten the payback on the pier.

Eleven claims about Lisbon's stopgap works, tested

Figures and statements that circulate about the South Pier, Terminal 2 and the capacity steps, checked against ANA, VINCI, the government and the regulator. Two of the errors were in our own research brief.

Compiled by Panos Bampalis, Portugal Trip Planner · Sources VINCI Airports releases (27 Nov 2024, 16 Jan 2026); ANA expansion report (31 Jul 2025, via IMT); portugal.gov.pt (5 Aug 2025); ECO; Jornal de Negócios; Observador; Sábado; DN · Verified October 2026
“ANA is investing €1 billion in Portela”FALSE
No ANA, government or regulator source gives €1bn for Humberto Delgado. The figures on record are €233M (main contract), €250M (South and Central piers), about €300M (Terminal 1 works) and "more than €300M" (VINCI's whole UPGRADE plan). The €1bn probably echoes the €1.15bn Montijo package of 2019, which was never built.
✓ What is true: ANA's Lisbon plan for 2026–28 is €388M, of which €64M is tagged to capacity.
“The South Pier opens in 2026”FALSE
VINCI's contract release (27 Nov 2024) says 2027; ANA's chief executive put completion at the end of 2027 (Jornal de Negócios, 7 Jan 2026), repeated by ANA in September 2026 (ECO).
✓ What is true: Completion is scheduled for the end of 2027. No month has been given.
“The expansion will let Lisbon handle 50 million passengers”MISLEADING
50 million was the combined Portela plus Montijo figure in the 2019 agreement. For Humberto Delgado alone the infrastructure minister's target is 40–45 million a year (ECO, 7 Jan 2026).
✓ What is true: 40–45 million is the official ambition for the existing airport.
“Lisbon will reach 45 movements an hour by 2030”UNSOURCED
No document attaches a year to 45. The government resolution (RCM 67/2024) and ANA's plan name 45 with no date. In Parliament on 28 Jan 2026 ANA's chief executive described 42 as the level at the transfer to the new airport.
✓ What is true: Only 38→40 has a work date (from early 2027). 40→42 awaits a second environmental study.
“Terminal 2 will close”NOT SUPPORTED
T2 reopened an enlarged Schengen departure area on 7 Jan 2026 after €12M of works (€20M since 2020). ANA's 2025 expansion plan says T2 needs no further building for 45 movements an hour.
✓ What is true: No closure is planned; ANA's plan keeps T2 in use with three new remote stands beside it.
“The new pier ends bus boarding”OVERSTATED
The contract adds 10 boarding bridges and also redesigns the South bus gates. Terminal 1 has about 47 gates, of which about 17 had bridges before the works (archived ANA data, indicative).
✓ What is true: Bus transfers fall but continue.
“The €12M Terminal 2 upgrade”INCOMPLETE
€12M is one phase. VINCI's own release (16 Jan 2026) gives €20M invested in T2 since 2020; press reports used either number.
✓ What is true: €12M for the 2025–26 Schengen phase, €20M in total since 2020.
“A €300M Mota-Engil project”CONFLATED
The €233M contract was signed with a four-company consortium led by Mota-Engil with VINCI Construction Grands Projets, Alves Ribeiro and HCI. VINCI Construction is a sister company of ANA's owner. €300M is the wider Terminal 1 programme.
✓ What is true: €233M main contract, Mota-Engil-led consortium including VINCI's own construction arm.
“42 movements means a plane every 81 seconds”ARITHMETIC
3,600 seconds ÷ 42 = 86 seconds. 81 seconds matches 45 movements (80 s). The figure appeared in coverage of the Lisbon mayor's opposition (DN, 15 Aug 2025).
✓ What is true: 42 an hour is one movement every 86 seconds; 45 is every 80.
“ANA's capacity plan was published in August 2025 (our own brief)”WRONG
The government announced on 5 Aug 2025 that ANA had delivered the plan on 1 Aug. The report, dated 31 Jul 2025, was posted by IMT only in February 2026, with no cost.
✓ What is true: Delivered August 2025, public February 2026, still uncosted.
“The Lisbon mayor opposes 42 movements (our own brief)”NOT FOUND
Carlos Moedas's recorded positions are against 45 an hour (ECO, 3 Sep 2024) and for compensation from VINCI (DN, 22 May 2024). We found no statement on 42.
✓ What is true: He opposes the 45-movement target and wants fewer flights.
💡 Most errors inflate the programme. The €1bn, the 50 million passengers, the 2026 opening and the 45-by-2030 date all make the stopgap look larger or faster than the record supports. The documented programme is a €233M pier contract inside a T1 programme of about €300M, plus a capacity plan that has no published cost and has so far reached its first environmental study.
Verdicts: FALSE contradicts the primary record; MISLEADING uses a real figure for the wrong scope; UNSOURCED has no traceable origin; NOT SUPPORTED has no current evidence; OVERSTATED exaggerates a real effect; INCOMPLETE gives part of a figure; CONFLATED merges separate items; ARITHMETIC is a calculation error; WRONG and NOT FOUND mark errors in our own brief. Gate counts are indicative (archived ANA pages via Wikipedia).

What this means for travelers, businesses and analysts

Travelers should expect Lisbon to feel like a building site until the end of 2027 and a crowded airport after that. The South Pier will put more passengers on boarding bridges, but it does not add flights, so peak-season delays and bus transfers continue. Terminal 2 is newly refurbished for Schengen low-cost departures. Non-EU visitors should leave time for the border. Our Lisbon travel guide covers getting into the city from the airport.

Tourism businesses and investors should treat Lisbon's capacity as fixed at 38 movements an hour until at least 2027 and 42 as the realistic ceiling before the new airport. The €64 million tagged to capacity in 2026–28 is a floor; the full cost of 40 and 42 has not been published. The R factor ties today's investment to Lisbon's charges from 2029, so higher spending now can mean higher airline costs in the airport's final years. The thresholds that would change this view are an APA decision on the 38 to 40 study, a court ruling on the 2024 exemption, a published cost for the 40 and 42 steps, and any slip in the Luís de Camões date.

Journalists and analysts can cite: the €233 million main contract (VINCI, 27 November 2024) with a four-company consortium; €250 million for the South and Central piers; about €300 million for all Terminal 1 works; €12 million for the 2025–26 Terminal 2 phase and €20 million since 2020; ANA's 2026–28 plan of €687 million, of which Lisbon €388 million and €64 million for capacity (ECO, 6 October 2026); ANA capex of €128 million in 2025; and the inflation-minus-2% cap for 2024–2028. Do not repeat "€1 billion for Portela", a 2026 opening for the pier, 50 million passengers at the existing airport, or 45 movements by 2030. This article adds a series finding: Lisbon receives the largest share of ANA's investment, but per passenger it ranks behind the Azores and Beja's near-empty terminal, and only a sixth of its planned money is aimed at the constraint that defines it. City-level context is in our Lisbon tourism statistics.

Data & sources

Period covered: Investment record 2019–2026 and ANA's plan to 2028; traffic 2019 and 2025 (Eurostat)

  1. VINCI Airports: main contract for Lisbon modernisation works · €233M contract, consortium, South Pier scope, completion 2027 (27 Nov 2024). Accessed 20 Oct 2026.
  2. VINCI Airports: Terminal 2 expansion completed · €12M Schengen phase, €20M in Terminal 2 since 2020, UPGRADE plan above €300M (16 Jan 2026). Accessed 20 Oct 2026.
  3. ECO: ANA vai investir 687 milhões até 2028 · ANA's 2026–28 plan by year and airport; Lisbon €388M split; 2025 capex €128M (6 Oct 2026). Accessed 20 Oct 2026.
  4. Jornal de Negócios: ANA já executou 40 milhões na expansão da Portela · €40M executed, T1 works ≈€300M, pier €250M, workforce, end-2027 completion, €16M check-in (7 Jan 2026). Accessed 20 Oct 2026.
  5. ANA: Relatório de expansão do Aeroporto Humberto Delgado (via IMT) · Stand requirements for 40/42/45 movements, North apron, airspace limits, Terminal 2 (report dated 31 Jul 2025, posted Feb 2026). Accessed 20 Oct 2026.
  6. APA: screening decision EnqAIA1844 · Taxiway U, outer taxiway and runway 20 entries require full EIA, baseline 38 up to 45 movements (2 Dec 2024). Accessed 20 Oct 2026.
  7. ANA regulated revenue and terminal passengers report 2025 · Lisbon group cap €14.652, collected €14.59; Lisbon airport €15.35 (20 May 2026). Accessed 20 Oct 2026.
  8. ANA Annual Report 2024 · R-factor mechanism, inflation minus 2% for 2024–2028, capex €100.8M (S.A.) / €105.0M (group). Accessed 20 Oct 2026.
  9. ANA Integrated Report 2025 · 2025 investment plan wording (€131M) and record net profit €599.3M. Accessed 20 Oct 2026.
  10. VINCI: 2019 agreement to expand Lisbon airport capacity · €1.15bn: €650M Humberto Delgado, €500M Montijo, 48 + 24 movements (8 Jan 2019). Accessed 20 Oct 2026.
  11. Observador: Ministério Público impugna obras no aeroporto de Lisboa · Action at the Supreme Administrative Court against the APA exemption and RCM 201/2023 (9 Jan 2025). Accessed 20 Oct 2026.
  12. Sábado: ANA entrega estudo ambiental para 40 movimentos · Two-phase EIA, 42 at transfer, CEO and chairman statements to Parliament (28 Jan 2026). Accessed 20 Oct 2026.
  13. Observador: ANA distribuiu 728 milhões em dividendos · Dividends 2023–24 and capex (26 May 2025). Accessed 20 Oct 2026.
  14. portugal.gov.pt: plano de expansão entregue no prazo · Government receipt of ANA's 45-movement plan, no cost (5 Aug 2025). Accessed 20 Oct 2026.
  15. Eurostat avia_paoa · Passengers by airport, 2019 and 2025, for per-passenger capex comparisons. Accessed 20 Oct 2026.
  16. ECO: Lisboa entre os piores aeroportos · AirHelp 2026 and Skytrax 2026 rankings for Lisbon (9 Jun 2026). Accessed 20 Oct 2026.
Methodology

This article draws on VINCI Airports and ANA releases and reports (contract release 27 November 2024; Terminal 2 release 16 January 2026; annual reports 2020, 2023 and 2024; Integrated Report 2025; regulated-revenue report 2025; the expansion report of 31 July 2025 posted by IMT), ANA's 2026–28 investment plan as reported by ECO and Jornal de Negócios, APA screening decisions, Diário da República resolutions RCM 201/2023 and RCM 67/2024, government statements at portugal.gov.pt, Eurostat airport data (avia_paoa), and Portuguese press (ECO, Jornal de Negócios, Observador, Sábado, DN, RTP, Lusa). Key ECO and Negócios figures were re-read in the original Portuguese. INE's site was not reachable; no INE figure is used directly.

Limitations: (1) ANA does not publish Lisbon-only capex by year or an audited total for the Humberto Delgado programme; the figures used are contract values, press-reported ANA statements and a three-year plan. (2) The 2026–28 figures are plans in a charges consultation, not realised spending. (3) ANA's annual reports for 2019 and 2021–22 could not be read for capex. (4) The phase dates in ANA's July 2025 report (Table 23 and Figure 46) could not be extracted. (5) Gate counts come from archived ANA pages via Wikipedia and are indicative. (6) International comparators rely partly on press and secondary sources.

Where sources disagree we publish both values and state which we use: contract figures over press summaries for the pier's scope, ANA S.A. capex where the +27% growth figure matches that basis, and Eurostat passenger counts for per-passenger ratios. Every number we calculated is marked as derived. Statements by ANA, VINCI and the Confederação do Turismo are treated as self-reported.

Notes on the data

Gaps: no published cost for the 38→40, 40→42 or 42→45 capacity steps or for ANA's August 2025 plan; no Lisbon-only capex series; no passenger-per-hour or annual capacity figure for the South Pier or Terminals 1 and 2; no published share of bus boarding or count of contact versus remote stands; no APA decision or public-consultation data for the 38→40 study by October 2026; no ruling in the Ministério Público case; no public concession clause on residual value or compensation for stopgap assets; no Schengen allocation for the pier.

Contested figures: the programme value is given as €233M (contract), €250M (South and Central piers), about €300M (all Terminal 1 works) and more than €300M (VINCI UPGRADE plan); Terminal 2 as €12M (phase) or €20M (since 2020); 2025 network capex as €128M (realised, ECO) or €131M (plan wording, ANA Integrated Report); pier as 10 bridges and 12 stands (VINCI contract) or 11 bridges and 3 stands (ECO, 28 Sep 2026); the 2019 Portela target as 48 (VINCI) or 44 (DN) movements an hour; the 2019 deal as €1.15bn, €1.3bn or €1,326M by scope; ANA's 2022 report says the 2023 Lisbon cap rose at inflation plus 2%, which conflicts with later reports.

Failed claims: €1bn for Portela (no source); South Pier opening in 2026 (end-2027); 50M passengers at the existing airport (combined Portela and Montijo figure from 2019); 45 movements by 2030 (no dated source); Terminal 2 closing (no evidence); the pier ending bus boarding (overstated); a €300M Mota-Engil project (conflated); 42 movements as a plane every 81 seconds (86 seconds). Two errors were in our own research brief: that the government published ANA's plan in August 2025 (it announced receipt; IMT posted it in February 2026) and that the Lisbon mayor opposes 42 movements (no statement found; he opposes 45). Our brief also attached RCM 119/2026 to Figo Maduro; ANA's report cites RCM 136/2025 for that transfer.

Derived figures: €7,060 per m² and €23.3M per bridge; ≈27 bridge gates after the pier; €93M unassigned in Lisbon's plan and €18M unassigned network-wide; capex per passenger for each airport; dividends 3.9× capex; €554.6M Lisbon regulated revenue in 2025; seven to nine and a half years of pier use; 86 and 80 seconds per movement. The link between 2023–27 capex and charges from 2029 is our inference from the R-factor rules, not an ANA statement.

Self-reported: VINCI's "largest capex contract" claim, ANA's statements on completion dates and capacity levels, EY/Confederação do Turismo delay-cost estimates, and AirHelp's undisclosed sample.

Panos Bampalis

Founder · Portugal Trip Planner

Frequently asked questions

What is the South Pier at Lisbon airport?

It is a 33,000 m² extension of Terminal 1 with 10 boarding bridges and 12 aircraft stands, plus a remodelled Central Pier and redesigned South bus gates. ANA signed the €233M main contract on 27 November 2024 and expects completion at the end of 2027.

How much is ANA investing in Lisbon Humberto Delgado airport?

The main contract is €233M, the South and Central piers are valued at €250M and all Terminal 1 works at about €300M. ANA's 2026–28 plan allocates €388M to Lisbon, of which €64M is labelled as capacity projects (ECO, 6 October 2026). No audited programme total exists.

When will the South Pier open?

ANA says the end of 2027 and has not given a month. Reports that it opens in 2026 are wrong.

Will the expansion add more flights at Lisbon airport?

Not by itself. The pier improves boarding and stands but ANA has called it a quality project. More flights depend on taxiway and runway-entry works that need environmental approval: 38 to 40 movements an hour from early 2027 if approved, then 40 to 42, with 45 undated.

What happened to Lisbon's Terminal 2?

An enlarged Schengen departure area with four new gates and biometric boarding opened on 7 January 2026 after a €12M phase; total investment in Terminal 2 since 2020 is €20M. No closure is planned before the whole airport is decommissioned.

Is ANA investing €1 billion in Portela?

No source supports that figure. The €1bn probably echoes the €1.15bn 2019 agreement, of which €650M was for Portela and €500M for Montijo, which was never built after ANAC refused to assess Montijo in March 2021.

Who pays for the Lisbon airport works?

ANA finances them and recovers costs through regulated charges capped per passenger. Lisbon's cap rises at inflation minus 2% in 2024–2028 because past investment was low; capex in 2023–2027 sets the adjustment for 2029–2033, so today's works can raise charges from 2029.

How many passengers can Lisbon airport handle after the expansion?

ANA publishes no passenger capacity for the pier. The government's target for the existing airport is 40–45M passengers a year, against 36.1M in 2025. The 50M figure that circulates combined Portela and Montijo in the 2019 plan.

What happens to the investment when the new airport opens?

The concession's treatment of residual value is not public. A legal opinion for the government says the State can end the concession before flights stop, with compensation due. The land is public and the minister says it will go to housing and parks, not to fund the new airport.